Sheet Pile Installation in Angke River to Finish December
access_time November 26 2015 10:50 AM remove_red_eye 3606
Reported by Septradi Setiawan | Translated by Trias Risangayu
Reported by Septradi Setiawan | Translated by Trias Risangayu
The sheet pile installation in
Angke River, Pesing Poglar, Kedaung Urban Village, Cengkareng, West Jakarta
keeps accelerating. The target is to finish in upcoming December.
We seem to have problem at the bottom due to many rocks
Baru River's Sheet Pile in Pasar Minggu Collapsed
“We seem to have problem at the
bottom due to many rocks. It is targeted to finish before
A 15 meters-sheet pile by 10 tons
weight will be installed with 100 meters distance. It merely 65 sheet piles installed
from the total of 250 sheet piles.